The Sarjeant Company Limited

On June 15, 2022, the MECP granted The Sarjeant Company Limited the required ECA and PTTW approvals. Many items on the original application were altered or removed for example a geosynthetic liner beneath the wash pond was required, a questionable secondary source pond below the pit was removed, strict monitoring was to be implemented and the license term was reduced to 5 years. Council reacted favourably to these changes.

Supporting Documents

Burnside’s report to Council on ECA and PTTW applications 27/6/2022

ECA approval by MECP released June 17, 2022

PTTW approval by MECP released June 17, 2022

MidlandToday article, 5 July 2022, Waverley Pit gets permit approvals from ministry, Tiny council


In early 2021, The Sarjeant Company Limited submitted a proposal for a new Permit to Take Water to take water from two ponds in Tiny Township for the purpose of aggregate washing.

  • Instrument type: Permit to take water
  • ERO number 019-3146
  • Ministry reference number 7577-BY4LDA
  • Site address: 1379 Baseline Road South, Tiny, ON, Canada

Supporting documents

Full PTTW Application released April 8, 2021

Harden Environmental Services Limited – Waverley Pit 2 PTTW Hydrogeology Report Aprilproduced after Sarjeant’s application

Harden Environmental Services Limited – Redacted page 8- PTTW Hydrogeology Report April 2021

Burnside report on PTTW application 15/4/2021

Tiny Council discussion of the proposal April 7th, 2021

ERO original application

Available proposal details

This proposal is for a new Permit to Take Water for The Sarjeant Company Limited to take water from two ponds for the purpose of aggregate washing. The details of water taking are as follow:

Source name: Pond A

  • purpose of taking: aggregate washing
  • maximum rate per minute (liters per minute): 1,140 liters
  • maximum number of hours of taking per day: 24
  • maximum volume of taking per day: 1,641,600 liters
  • maximum number of days of taking in a year: 180
  • earliest calendar date of taking (mm/dd): 03/01
  • latest calendar date of taking (mm/dd): 12/31
  • length of taking: 10 years

Source name: Pond B

  • purpose of taking: aggregate washing
  • maximum rate per minute (liters per minute): 1,140 liters
  • maximum number of hours of taking per day: 24
  • maximum volume of taking per day: 1,641,600 liters
  • maximum number of days of taking in a year: 180
  • earliest calendar date of taking (mm/dd): 03/01
  • latest calendar date of taking (mm/dd): 12/31
  • length of taking: 10 years